When drafting, how do I get the base view to be created in WCS and not absolute csys

posted by Feb 10, 2015 in General Forum by Sam2015 (120 points)

Please log in or register to answer this question.

1 Answer

0 votes
answered Feb 16, 2015 by Ronaldvandenbroek (9,690 points)

In modeling position your model in the wcs you want on drawing and then save-as view. Give it a proper name and you should be able to select that view as a base view of your drawing.